How to Manually Add a Transmittal in Sage Construction Management

How to Manually Add a Transmittal in Sage Construction Management


Welcome! In this tutorial, you'll learn the process of manually adding a transmittal within Sage Construction Management. Whether you're working through projects or leads, these steps will guide you to ensure your transmittal is submitted correctly.




Starting with Projects

From the homepage, navigate to the 'Projects' section. You may select a project from the list or use the hyperlinks provided.

Choosing the Right Project

Click on the project for which you need to submit a transmittal. Then, scroll to the 'Correspondence' section and select 'Transmittal'.

Adding a Transmittal Manually

Once you're in the Transmittal section:

  • Click on 'Actions' and select 'Add Manually'.
  • The project number, issue date, and transmittal number will be auto-filled but can be modified if necessary.
  • Enter the subject of the transmittal. This is required.
  • Fill in the type, sender, and due date. These fields are optional but recommended for clarity.

Customizing Sender Information

The 'From' field is pre-populated with your information but can be changed. You can also toggle between different addresses.

Adding Comments and Attachments

While comments are optional, you can enhance your transmittal by adding notes, links, or photos.

Referencing Items

Include any references relevant to the transmittal to ensure all information is accurately conveyed.

Itemizing the Transmittal Package

Detail the items included in the transmittal:

  • Specify the item and its description.
  • Quantity, return quantity, units, and 'Transmitted For' fields are optional.
  • Adjust the numbers as necessary.
  • Click 'Add' to include each item in the transmittal.

Uploading Files

Drag and drop files, link to existing documents, or add new files to the transmittal. If there are no files to attach, you may skip this step.

After adding your files, the transmittal is complete. You can edit it by selecting the appropriate option.

Conclusion

Following these steps will ensure your transmittal is added manually and accurately within Sage Construction Management. Remember to review all details before submission for a seamless correspondence process.



    • Related Articles

    • How to Manually Add Specifications to Sage Construction Management

      Welcome to our knowledgebase. In this article, we'll guide you through the process of manually adding specifications to your projects in Sage Construction Management. This is a crucial step for maintaining accurate and comprehensive project data. ...
    • How to Manually Add a Submittal in Sage Construction Management

      Welcome to our comprehensive guide on how to manually add a submittal in Sage Construction Management. This article is designed for project managers and construction professionals looking to streamline their submittal process using Sage software. ...
    • How to Manually Add a Journal in Sage Construction Management

      Welcome to our guide on how to add a journal entry within Sage Construction Management. Whether you're dealing with leads or projects, this step-by-step tutorial will assist you in keeping your project documentation up to date. Starting from the ...
    • How to Manually Add a Drawing Log in Sage Construction Management

      Welcome to our guide on manually adding a drawing log to your project in Sage Construction Management. Whether you're a seasoned professional or new to the platform, this article will walk you through the process step-by-step. Starting from the ...
    • How to add a user in Sage Construction Management

      If you have an Administrator role assigned to you in Sage Construction Management, you have the ability to add additional users in the system. To add a user, please follow these general instructions: Login to Sage Construction Management: ...