Adjusting AR Invoices with Retainage in Sage 300 CRE
Overview
In this article, we'll guide you through the process of adjusting Accounts Receivable (AR) invoices with retainage in Sage 300 CRE. We'll use an example based on data from a test company to make the steps clearer.
Example Scenario
Let's consider an invoice for $1,000 with a 10% retainage. This means that the net invoice amount is $900, with $100 being the retainage. Refer to the image below for a visual representation:
1. Adjusting the Invoice Amount:
- Our task is to adjust the invoice down to $600, minus the 10% retainage, which amounts to $60.
- After the adjustment, the new invoice amount should be $560, with a retainage of $60.
- To achieve this, we will reduce the invoice by $400, excluding the retainage of $40.
2. Enter Adjustment Details:
- Go to AR > Task > Adjust Receivables.
- Select the client in question.
- Enter the Adjustment Date on the right.
- Select the invoice from the list below.
- Click "Adjust..." to proceed with the adjustment.
3. Adjusting the Invoice
- On the next screen, keep the Adjustment Type as "Bill Credit."
- Enter the Adjustment Date on the left side.
- At the top, enter the total amount of the adjustment. In our example, we are adjusting the invoice by $400 and $40 of retainage, resulting in a current amount of $360 and retainage of $40.
- Once the date and amounts are entered, click on the "Distribution" button to allocate the amount to each distribution line.
- If you are adjusting an invoice with a single line, there is no need to change anything under the Distribution section.
- Click "Finish" and then "Finish" again to complete the adjustment.
- Finally, post the entries to save the changes.
4. Impact of the Adjustment:
After completing the adjustment, the following changes will occur:
- The original invoice amount of $1,000 will be adjusted to $560.
- The retainage will decrease from $100 to $60.
- The invoice has been successfully adjusted in Sage 300 CRE.
Conclusion:
Adjusting AR invoices with retainage in Sage 300 CRE is a straightforward process that involves selecting the invoice, specifying the adjustment amount, and distributing it accordingly. Following these steps will help you accurately adjust your invoices as needed.
Related Articles
2024 Year-End | Sage 300 CRE & Sage 100 Contractor
Prepaa4rations for Year-nd Sage It’s that time again! Calendar year 2024 is wrapping up and 2025 is about to start. That means the Sage year-end software upgrades are just around the corner, and we’re here to help make that as smooth a process as ...
QuickAim Manuals for Sage 300 CRE
We have attached QuickAim Manuals to this article for your convenience. Here is a brief overview of what each manual covers: See the Attachments section to download the correlating manual QuickAim Core - (AB AP CM GL IA PR TX) Address Book Accounts ...
AP Payment Process in Sage Intacct vs Sage 300 CRE
Introduction This article provides a step-by-step guide on the Accounts Payable (AP) payment process in Sage Intacct Construction compared to Sage 300 CRE (formerly Timberline). The detailed video tutorial can be viewed here. Single Payment Scenario ...
What is a Sage 300 CRE System Review?
Our Sage 300 CRE System Review is a comprehensive review of your system over the course of five, 1.5 hour sessions. Our team will provide you with quick wins and best practices, along with final recommendations throughout. *Please note that System ...
Adjusting Payroll Checks in Sage Intacct
In this comprehensive guide, Mike Baio from Bangert walks through the process of making adjustments during the payroll check processing in Sage Intacct. Whether it’s before or after payroll checks are approved, or even when importing adjustments, ...